Production takes 45 to 50 days after artwork approval, exactly as it does for any other order. What makes a government order take longer overall is the procurement process on your side, not the manufacturing on ours.
The full path, with both halves stated:
- Request a quote. Free, with no commitment. Ask for it formatted for your file.
- Vendor verification. Checking our SAM registration, UEI F3AGRUW5RT53 and CAGE code 1AYR0. Usually quick.
- Requisition and approval. Internal, and the stage that varies most. A micro-purchase on a purchase card can be same-day. A purchase order through a contracting office takes considerably longer.
- Artwork and approval. Initial artwork is usually ready within 12 to 48 hours, then approval rounds through your chain of command.
- Production. 45 to 50 days from written approval.
- Delivery. Free within the continental United States, with APO and FPO available.
The step agencies most often underestimate is step 3, because it is the one nobody schedules. A coin order held three weeks awaiting a signature has consumed three weeks of the timeline with no production progress.
Working back from an event, allow 10 to 12 weeks minimum, and more if a contracting office is involved.
See how agencies buy coins, or request a free quote with your date.